Earned Schedule – application of the To Complete Schedule Performance Index

Presenter:

Paper Summary

This presentation details recent analysis using real data that has shown that the value 1.10 for TCPI and the To Complete Schedule Performance Index (TSPI) from Earned Schedule is a definitive and reliable performance threshold. This presentation describes the use of Earned Value Management/Earned Schedule project performance measures with the established threshold to compute the probability of cost and schedule recovery. Utilizing the computed probability, a schedule performance improvement strategy is discussed for achieving project recovery. The application of the recovery probability and strategy enhances the likelihood for having a successful project.